2026-04-25__001_synthetic_mine_throughput__pi-agent__gemini-3-1-pro-preview__vanilla-customtools

Date: 2026-04-25 · Benchmark: 001_synthetic_mine_throughput · Harness: pi-agent · Model: gemini-3-1-pro-preview (vanilla-customtools) · ✓ Autonomous

Scores

Category Points Max
Conceptual modelling 14 20
Data and topology 12 15
Simulation correctness 14 20
Experimental design 11 15
Results & interpretation 11 15
Code quality 7 10
Traceability 4 5
Total 73 100

Run metrics

Evaluation report

Scenario Mean throughput
baseline 12,416.667
trucks_4 8,126.667
trucks_12 12,666.667
ramp_upgrade 12,440
crusher_slowdown 6,440
ramp_closed 12,416.667

Source files

Downloads

Conceptual model

Conceptual Model Design

System Boundary

The simulation models the active haulage operations over an 8-hour shift. It includes:

Entities

The primary active entities moving through the system are Trucks. Each truck cycle consists of:

  1. Routing from its current location to an available loader.
  2. Traveling empty to the loader queue.
  3. Loading an ore payload.
  4. Routing from the loader to the primary crusher.
  5. Traveling loaded to the crusher queue.
  6. Dumping the payload.
  7. Repeating the process.

Resources

The system is constrained by:

Events

Key discrete events tracked in the simulation include:

State Variables

Tracked state includes:

Assumptions

Performance Measures

README

Synthetic Mine Throughput Simulation

This project implements a discrete-event simulation of a mine haulage network using SimPy and NetworkX. It estimates ore throughput to a primary crusher over an 8-hour shift under various operational scenarios.

Installation & Requirements

Ensure you have Python 3.8+ installed. The simulation requires the following dependencies:

pip install simpy networkx pandas numpy scipy pyyaml

Running the Simulation

Execute the main simulation script, which runs 30 replications for all 6 required scenarios:

python3 sim.py

This will generate:

Conceptual Model & Assumptions

Please refer to conceptual_model.md for details on system boundaries, entities, state variables, and resource definitions.

Routing and Dispatching Logic

Operational Decision Questions

1. What is the expected ore throughput to the crusher during the baseline 8-hour shift?

The baseline configuration delivers approximately 12,416 tonnes per shift (1,552 tonnes per hour) with a 95% confidence interval of roughly [12,341, 12,491].

2. What are the likely bottlenecks in the haulage system?

In the baseline, the Crusher operates at around 90-91% utilisation, while trucks experience minor queuing at the loaders. As the fleet grows, the Crusher becomes the absolute constraint, generating long queues.

3. Does adding more trucks materially improve throughput, or does the system saturate?

The system saturates. Increasing the fleet from 8 to 12 trucks yields negligible additional throughput (rising slightly to 12,666 tonnes), but crusher queues skyrocket to 14.9 minutes. Decreasing the fleet to 4 trucks severely drops throughput (to 8,126 tonnes). The baseline 8-truck fleet is optimal for this crusher capacity.

4. Would improving the narrow ramp materially improve throughput?

No. The ramp upgrade scenario delivers ~12,440 tonnes, practically indistinguishable from the baseline. This is because trucks only traverse the ramp once during the initial dispatch from parking. Subsequent cycles occur entirely in the upper network.

5. How sensitive is throughput to crusher service time?

Extremely sensitive. The crusher_slowdown scenario cuts throughput by nearly half (to 6,440 tonnes). Crusher queues explode to 28 minutes, bottlenecking the entire cycle. Since the crusher operates continuously near 90%+ utilisation in baseline, any degradation immediately impacts production.

6. What is the operational impact of losing the main ramp route?

Negligible to zero. In the ramp_closed scenario, throughput remains at ~12,416 tonnes. Trucks simply take the western bypass from PARK to the loaders. Since this detour is only taken once at the beginning of the shift, the 8-hour steady-state throughput is completely unaffected.

Limitations

Reviewer form

Reviewer Form: Synthetic Mine Throughput

Submission: 2026-04-25 / 001_synthetic_mine_throughput / pi-agent / gemini-3-1-pro-preview / vanilla-customtools Reviewer: Independent human reviewer (opus subagent) Date: 2026-04-27

Automated report

Human quality score

CategoryMaxScoreNotes
Conceptual modelling2014conceptual_model.md covers all eight required headings, separates derived vs introduced assumptions, and names limits. But it is thin: only two loaders enumerated, no listing of which constrained edges (E03/E05/E07/E09) are modelled as resources, no warm-up discussion, performance-measure section under-specifies how utilisation is calculated. Adequate but lacks operational depth.
Data and topology handling1512Reads all five CSVs and YAML; builds a networkx.DiGraph with edge weight distance / (speed*1000/60); correctly applies edge_overrides, node_overrides, dump_point_overrides, and fleet.truck_count; respects closed: true by skipping the edge. Constrained edges (capacity < 999) become simpy.Resource (sim_core.py lines 70-73), which is meaningful. Minor issues: graph weights ignore the loaded/empty speed factor (acceptable since factor is uniform across edges), the routing graph uses raw max_speed rather than scenario-aware time, and the magic constant 999 for “unconstrained” is hardcoded.
Simulation correctness2014Genuine SimPy DES with truck processes, loader/dump/edge resources, and with resource.request() blocks (sim_core.py lines 160, 175, 212, 227). Tonnes are correctly accumulated only on dump completion (line 242). Single-lane edges are held for the entire traversal — correct. Concerns: (i) random.gauss is plain Gaussian clipped at 0.1, not the truncated-normal claimed in the conceptual model; (ii) truck truck_active_time is double-counted — every actual_time and actual_load/actual_dump is added even though the truck is idle while waiting in queue, which is fine, but the same minutes are counted whether the truck holds an edge or queues for one (active-time accumulates only after the timeout completes, so this is OK on inspection); (iii) the dispatch policy uses q_len * mean_load_time_min as expected wait, which ignores the residual service time of the truck currently being loaded — minor heuristic limitation; (iv) loader_busy_time dict is populated but never reported. No major correctness defects, but small simplifications.
Experimental design151130 replications per scenario, deterministic seed 12345 + i (sim.py lines 10, 47), 6 required scenarios run. CIs computed via Student-t in mean_ci (line 29). Stochasticity applied to load, dump, travel times (CV 0.10). Weaknesses: warm-up explicitly set to 0 with no justification (the README claims steady-state yet startup transient is included in throughput); no additional scenarios proposed despite the prompt inviting one (additional_scenarios_proposed: []); narrow CIs (~0.6%) suggest the noise model may be too tame given a 100-tonne discretisation.
Results and interpretation1511All six decision questions are addressed in README.md with numerical values and a clear narrative (saturation at 8 trucks, crusher as primary bottleneck, ramp upgrade and ramp closure both immaterial). The interpretation that the ramp is irrelevant because “trucks only traverse it once” is correct given the topology and shortest-time routing — verified T01 in baseline takes PARK→J1→J2→J7→J5 (bypass) initially, then never returns to J2. However, no per-loader utilisation reported (loader_utilisation: {} left empty in summary.json), top_bottlenecks is mechanical (single string, threshold-based), and there is no discussion of confidence interval widths or what would improve throughput beyond restating the crusher constraint.
Code quality and reproducibility107Two-file layout (sim.py orchestration, sim_core.py model) is reasonable. README has clean run instructions (python3 sim.py) and pip command. Negatives: hard-coded relative paths ('data/nodes.csv') require running from the submission root; literal 'CRUSH' destination string in sim_core.py line 193; simulation dict assumed to exist on line 251; only 12 comment lines across 275 code lines (per evaluation_report); no type annotations, no tests, no requirements.txt/pyproject.toml. Adequate for a 300-line script, not exemplary.
Traceability and auditability54event_log.csv has 392k rows with the required columns (time_min, replication, scenario_id, truck_id, event_type, from_node, to_node, location, loaded, payload_tonnes, resource_id, queue_length). Event types include travel_start/end, queue_start, load_start/end, dump_start/end. Traced T01 across one full cycle and the route is auditable end-to-end. Minor issues: queue_length only logged at queue_start (not on each departure); resource_id blank on travel events; no loader_busy_time output, so per-loader utilisation cannot be reconstructed without re-aggregation.
Total10073

Top 3 strengths

  1. All behavioural sanity checks pass and the numbers tell a coherent story. baseline 12,417 t, trucks_4 8,127 t, trucks_12 12,667 t (saturation), crusher_slowdown 6,440 t, ramp_closed = baseline. The crusher_utilisation ~0.91 in baseline is consistent with the saturation conclusion.
  2. Genuine SimPy DES with constrained-edge modelling. Single-lane edges (capacity < 999) become simpy.Resource and trucks acquire/release them via with blocks — not a static spreadsheet calculation.
  3. Working dispatch heuristic and event log allow audit. The shortest-time + queue-aware loader choice is documented in the README and visible in code (sim_core.py lines 117-136), and the event log permits per-truck cycle reconstruction.

Top 3 concerns or gaps

  1. Loader utilisation tracked internally but never reported (stats['loader_busy_time'] populated, but loader_utilisation: {} empty in summary.json). The recommended schema explicitly asks for it, and it’s needed to identify whether LOAD_N or LOAD_S is the binding loader.
  2. No warm-up handling and no additional scenario proposed. Warm-up is set to 0 with no justification despite a known startup transient (8 trucks dispatched simultaneously from PARK), and the prompt’s invitation to propose one extra scenario was not taken — a missed analytic opportunity.
  3. Conceptual model and code show small inconsistencies and shortcuts. Truncated-normal claimed, plain Gaussian + clip used; 999 used as a sentinel for unconstrained capacity; bottleneck classification is a heuristic threshold rather than a derived measure; only 12 comment lines in 275 LOC; no requirements.txt.

Failure modes observed

Final judgement

Marginal-to-acceptable submission. Trustworthy as a first-pass decision-support artefact, partially.

The simulation is real DES, results are internally consistent, scenarios are correctly perturbed, and the decision questions are answered with defensible numbers. However, the analysis is shallow (no per-loader utilisation, no warm-up reasoning, no proposed scenarios, terse interpretation), the code is minimally documented, and the conceptual model glosses over operational detail. Final score: 73/100. Useful to bracket throughput estimates and inform the conversation, but would not commission capex on the ramp purely based on this output without additional analysis on the bypass-vs-ramp routing assumption.

← Back to leaderboard